Our major roadworks on Calala Lane near Farrer Memorial Agricultural High School are past the halfway mark and are expected to be finished in June.
The widening of the table drain alongside the roadway is complete. It will increase the road's durability and ability to cope with weathering.
Good progress is being made on the intersection of Loomberah Road and Calala Lane. Base layer and sealing works are now well underway.
We thank all drivers who use this busy section of local road for their patience with the unavoidable traffic delays as we work to improve Calala Lane.